Located in the heart of the Edwards Limestone, this master plan development took an extra level of effort to carve into the surrounding environment. A notoriously hard and challenging formation to work in, every inch of underground utilities required rock trenching and a high degree of effort from the Cast team to deliver on time and in budget.
PROJECT HIGHLIGHTS:
-
434 Single Family Lots
-
45,000 LF Wet Utilities
-
54,000 SY Streets (Subgrade, Base, Paving, and Curb)
-
230,000 CY Rock Excavated and Placed